This $24 million project involved constructing a building to house three 2,500-HP pumps and their associated piping. The interconnecting pipeline outside the pump station was also included in the standard bid-build contract.
This award-winning project allows migrating salmon and steelhead trout to bypass the Bonneville Dam and travel safely through the Columbia River. Kiewit Pacific Co. ultimately constructed a 3,000-ft.-long, high velocity concrete chute with 25-ft.-high walls to transport fish around the dam and through a new channel outfall.
East Dam is one of three dams constructed for the Metropolitan Water District of Southern California's Eastside Reservoir program. Holding more than 260 billion gallons of water, the reservoir doubles Southern California's surface storage capacity. At 180 feet high and 1,200 feet wide at the base, East Dam is the longest of the three dams.
The largest brackish water desalination plant in North America has the capacity of 27.5 MGD to meet the needs of both Ft. Bliss and El Paso Water Utilities. With the constraints of a 22-month schedule from notice to proceed to substantial completion, Kiewit performed all structural concrete work, set all embed items for mechanical equipment and structural steel, installed pumps and piping, RO skids chemical systems and equipment, and performed start up and commissioning.
This $208 million project involves upgrading the Orange County Wastewater Treatment Plant No. 1 in Fountain Valley, CA. The upgrade, which will add a secondary treatment capacity of 60 MGD, is slated to be complete by 2012.
Working at a depth of 80 feet, crews from Kiewit Pacific Co. pumped groundwater from the excavation site at a rate of 14 million gallons per day to construct New Natomas and South River Pumping Stations. The scope of work at each site involves excavation support, dewatering, constructing new below-grade and at-grade concrete structures and installing mechanical equipment.
As the primary water source for the Contra Costa Water District, the Los Vaqueros Dam measures 1,000 feet across and 192 feet high. During construction, project personnel suggested a value engineering concept that considered the creation of rip rap from on-site oversized rock from the excavation. This resulted in more than 50,000 cubic yards of rip rap generated on-site.
The Val Vista Transmission Main Rehabilitation and Replacement project, delivered in seven GMP’s, was the largest project of its kind in the United States., The project was developed to trenchlessly rehabilitate a critical piece of infrastructure that transports 220 MG of drinking water to as much as 60 percent of the population in Phoenix, Arizona. The project involved the rehabilitation of 30,000 feet of 96-inch to 72-inch prestressed concrete cylinder pipe by means of a split-can, steel slip lining.
Kiewit Pacific Co. was awarded an $18 million contract to rehabilitate 12 rectangular primary sedimentation tanks. Crews will replace grit slurry piping and grit overflow piping in grit handling areas as well as constructing related structural, mechanical and electrical work.
This $20 million project involves replacing the existing sewage pump station with a new upsized 39 MGD pump station. Construction on the new pump station includes a below-grade wet-well and dry-well, and an above-ground electrical room.