InterGen selected Kiewit to provide owner's engineering services for their new 230 MW gas-fueled combined cycle project in Queretaro, Mexico. Kiewit's services included: detailed review of documentation developed by the EPC contractor; support of monthly project reviews; tracking contractor submittals and schedule performance; on-site oversight during construction and commissioning; and owner's representative for all aspects of plant performance testing and acceptance
The Lower Mattagami River Project is an investment into clean, renewable energy. It is the largest hydroelectric power generation initiative in nearly 40 years in Northern Ontario. Ontario Power Generation (OPG) selected Kiewit-Alarie, a Partnership (KAP) to administer the design-build project on the Mattagami River
Mass. Electric Construction Co (MEC) installed an 880 KW roof mounted PV system on the Waltham High School in Massachusetts. The scope of work included PV modules- 3080 each LG250 mods; inverters 2 each- Solaron 333kW; an Hb Solar Mounting System (100% ballasted) including ballast; Solar BOS fused Combiner Boxes; Data Acquisition System (DAS); and (8) 200A rated Fusible DC Disconnect.
The Kiewit team engineered, procured and constructed the 800 MW natural gas-fired facility with four 200 MW Siemens 5000F(4) simple cycle units and selective catalytic reduction (SCR), oxidation catalysts, exhaust gas-tempering air fan systems and three fuel gas compressors.
The project included the design and construction of transmission structure foundations, including upgrading and converting existing 138kV to 230kV with new structures, power conductors and OPGW. The project also incorporated the demolition and reinforcement of existing 138kV structures.
The Antelope Station Grid Switching Expansion Project will allow an existing generating station to switch between the SPP and ERCOT grid systems. Kiewit Engineering and Design is designing the switch to a grid configuration consisting of a single-breaker, double-bus.
The Kiewit team was awarded the contract to design and install the Ghent Coal Combustion Residuals (CCR) Transport Project. Upon completion, it will condition, dewater and transport CCR from the four coal-fired boilers to a remote landfill storage. The project includes the installation of a pneumatic system for conveying fly ash, including fly ash storage silos, gypsum dewatering facility and bottom ash dewatering facility. The ash handling project incorporates a 1.8-mile overland pipe conveyor for transporting the dewatered CCR to a landfill.
To decrease the cost of hydroelectric power and increase the demand for service, Kiewit completed this bid-build contract to expand the Healey Falls Generating Station. Located about 15 kilometers north of Campbellford, the generating station includes a new unit in a spare bay inside the existing hydroelectric power plant once complete.
Working in a limited space with a five-week outage duration, the Kiewit team engineered, procured, constructed and performed startup of the air quality control system to tie it into Brayton Point’s Unit 3 at New England’s largest fossil fuel-fired power station.
Mass. Electric Construction Co (MEC) installed one of the largest community solar projects in Massachusetts. Situated on 200 acres of the historic St. Joseph’s Abbey, the Spencer Community Solar Farm is 100% subscribed with a rating capacity of 14.7 MW (AC). This installation is comprised of more than 61,000 solar photovoltaic panels powering 1,500 local homes.