Kiewit subsidiary, TIC, constructed the Billy Miner I central gathering facility (CGF) near Pecos, Texas. Noble Energy’s overall integrated development plan included multiple CGFs, which are connected in a supernode design to maximize flexibility, to minimize costs and to meet drilling schedule requirements.
TIC also expanded the facility by constructing Billy Miner II, a second standalone greenfield CGF. With this addition, the facility processes around 30,000 barrels per day of produced oil, 30,000 barrels per day of water and 40 million standard cubic feet per day of gas from wells in Noble Energy’s Permian Basin assets to support its drilling schedule.
After completing both CGFs, TIC was contracted to remove and repair damaged compressor station equipment during a shutdown.