Kiewit, one of the largest transportation contractors in North America, constructs and upgrades interstate; highways and bridges; rail lines and rail yards; urban mass transit systems; and airport runways, taxiways and associated facilities. Kiewit’s capabilities are reinforced by one of the largest privately-owned fleets of construction equipment in North America, which enables the company to rapidly mobilize the necessary resources for any project. Engineering News-Record (ENR) consistently ranks Kiewit among the top transportation contractors in the United States. In 2015, Kiewit was ranked the No. 2 contractor in transportation, as well as No. 2 in bridges and mass rail, and No. 3 in highways. During the past 10 years, Kiewit constructed 1,000 transportation projects totaling nearly $30 billion in contract revenue. About 70 percent of these projects were delivered using negotiated procurement methods, including best value and A+B bids.
The U.S. Army Corps of Engineers awarded Kiewit an $20 million project to remove and rebuild the existing east and west breakwaters as well as dredge the navigational channel of Kikiaola Light Draft Harbor on the island of Kauai, Hawaii. A mining excavator with state-of-the art GPS technology is used to set stone for breakwater and excavate the existing jetty.
The passenger tunnel at Dulles International Airport allows travelers to move more efficiently through the fast-growing airport. Kiewit excavated the tunnel under a live taxiway using New Austrian Tunneling Method. The completed tunnel is lined with PVC waterproofing and reinforced cast-in-place concrete and is equipped with escalators and moving walkways.
Constructed for the U.S. Army Corps of Engineers, these aircraft weather shelters feature drive-through aircraft bays with mechanical/electrical support, tool storage, and administration areas. The 63-foot by 70-foot bays are separated by concrete “blast walls” containing all equipment needed for missile loading, fueling, and normal maintenance operations.
The $56 million Puget Sound Carrier Support Complex project included construction of a 1,680-foot-long by 126-foot-wide carrier pier and a 470-foot-long by 144-foot-wide marginal wharf for escort vessels. Ship service utilities included steam, potable water, sanitary sewer, and shore power electrical service and communications lines.
Work for this $13.5 million project included widening the eastbound side of the bridge, adding a new support arch to create room for another traffic lane and rehabilitation of the existing 132-metre structure.
This $22 million emergency repair contract provided structural stability to Graving Dock #3 after a sheetpile cell catastrophically erupted. Kiewit successfully dewatered the dock and strengthened the cell. The team's impressive performance led to a follow-on contract to provide permanent repairs to the dock.
After successfully completing the emergency repair contract at Graving Dock #3, General Dynamics awarded Kiewit the $38 million long term repair project. Crews developed an innovative concrete mix that allowed quick turnaround of formwork, enabling them to meet the project's demanding schedule.
This $22.5 million, 1,025-foot-long wharf extension at the National City Marine Terminal radically increased the cargo-handling capacity, permitting simultaneous berthing of two 700-foot-long ships capable of carrying as many as 2,000 vehicles each.
This container wharf - the largest in the country - is more than 4,000 feet long and can accommodate up to four container ships simultaneously. The project received a 1997 Marvin M. Black Award for Excellence in Partnering.
Kiewit completed this $8.9 million project to replace a 34-year-old air traffic control tower one month ahead of schedule. At an elevation of approximately 7,000 feet, crews constructed a new control tower, base building, emergency generator building and fuel containment area.